Data centres must match at least 80% of their electricity use with renewable power hour by hour under a decree the People’s Party (PP) has pledged to repeal if it wins the 29 November election.
Spain has approved a record €17.142 billion investment plan to expand and modernise its electricity transmission network by 2030, alongside new rules designed to prevent the country’s fast-growing data centre industry from driving up power bills. The cabinet approved both measures on Friday. The data centre rules, which also cover water efficiency and the handling of sensitive public-sector data, came into force on Sunday. ALSO READ: Repsol seeks €120 million from power companies over Iberian blackout.
Record grid investment puts industry first
The grid plan provides for new power lines, upgrades to existing ones, more substations and closer links with neighbouring electricity networks. It is designed to accommodate 47.4 gigawatts (GW) of additional demand as factories, homes and transport switch to electricity and new users seek connections. The investment is 146% higher than under the previous plan, approved in 2022, and around 30% above the figure initially put out for consultation, according to Spanish state broadcaster RTVE.
Industrial electrification and decarbonisation account for the largest share of the new demand, at 14.9 GW. The plan makes provision for a further 12.4 GW for renewable hydrogen and its derivatives, 9.3 GW for data centres and 6 GW for housing and regional development. Ecological Transition Minister Sara Aagesen (main image) said the housing allocation would be enough to serve up to three million highly energy-efficient new homes. The plan also provides for electrification in transport, ports and railways.
The cabinet also approved measures to help integrate renewable generation into the electricity system and to implement the EU’s new emissions trading scheme for buildings and road transport. ALSO READ: Reasons for Spain’s April power blackout: ‘overvoltage’ & ‘poor planning’.
Data centres face an hourly clean-power test
Under the Royal Decree, operators generally have to match at least 80% of the electricity they use in each hour with renewable power generated in the same hour. They must also show that their demand is backed by additional renewable capacity in Spain, subject to exceptions for some existing plants. Operators can use their own generation, long-term power purchase agreements and storage to meet the requirements. ALSO READ: Amazon to invest another €18bn in data centres in Spain, adding to €15.7bn announced in 2024.
A five-year transitional option gives operators more flexibility if they agree to be among the first users whose power supply can be cut when the grid comes under strain. The decree also sets interim water and energy efficiency standards while European criteria are being finalised, and requires larger facilities to report on their environmental performance.
For facilities hosting systems in the highest category of Spain’s National Security Framework, such as those handling critical health, tax, energy or transport information, the most sensitive data must remain within the European Economic Area. Operators must also control access from outside the area for administration, maintenance and technical support.
Projects that already have permits but have yet to connect generally have six months to demonstrate compliance with the applicable requirements. Pending applications generally have three months. Breaches of the renewable electricity rules can trigger compensation payments, and sanctions can include suspension of grid access and connection rights for up to three years.
Government warns of higher bills as industry pushes back
Data centres already hold grid access permits for around 15 GW, including about 3 GW that Aagesen said had emerged in recent months. Euronews reported that a further 20 GW was awaiting approval. The government’s concern is that the facilities need power around the clock, which could leave Spain burning more natural gas to generate electricity when renewable output is low.
‘In the absence of this Royal Decree, we would see an impact of 5,000 million euros on our bills,’ Aagesen said. The government’s estimate puts the potential annual cost at €4 billion in higher wholesale prices and another €1 billion in payments to ensure enough generating capacity is available. In one scenario, industrial users could pay 25% more for electricity. Both figures come from government modelling of what could happen if the sector expands without the controls.
Spain’s renewable resources, connectivity and availability of land have helped make it one of Europe’s fastest-growing locations for data centres.
The rules have brought the trade-off between attracting investment and managing the pressure on electricity and water supplies into the final days of the election campaign. Alberto Nadal, the right-wing PP’s deputy secretary for the economy, wrote on X that the rules ‘effectively bans the installation of data centres’ was their practical effect, and pledged to replace them with legislation that would allow projects to go ahead while protecting sustainability.
According to a Reuters report, Amazon Web Services and Microsoft have said their regional plans in Spain are unchanged. ALSO READ: Microsoft to invest €2.2 billion in huge data centre project in Aragón.
However, two executives at other companies developing data centres in Spain told Reuters that the electricity requirements would make many projects unprofitable and that they were looking at France and Portugal for future developments.
Enjoying the news from Spain in English? Add us as a preferred news source in Google.
Subscribe to the Weekly Newsletter from Spain in English.
El Gobierno establece los requisitos de sostenibilidad energética, medioambiental, resiliencia y soberanía digital de los centros de datos. ”Todos los centros tendrán que cumplir con la categoría A, fijada por la UE”, la vicepresidenta y ministra de @mitecogob, Sara Aagesen. https://t.co/ERKPSnkhe2
— La Moncloa (@desdelamoncloa) November 20, 2026